Project Details

Owner
City and County of Denver; Park Creek Metropolitan District
Location
Denver, CO
Date of Completion
Fall 2016

Project Description

Since 2013, Premier Earthworks and Infrastructure has been successfully completing several projects in the 4,700-acre Stapleton Redevelopment.

This includes:

  • Aurora Filing 1 & 2 concrete
  • Rocky Mountain Arsenal Waterline
  • Filing 43
  • Filing 45
  • Filing 47
  • Filing 49
  • District IV concrete paving and concrete box culvert

In total, these projects included over 3.7 million cubic yards of earthwork, 22 miles of pipe, 3,100 feet of concrete box culverts, and 8,700 cubic yards of concrete paving. One of the more difficult requests was constructing a 6’ x 13’ cast in place concrete box culvert under existing Conoco/Phillips fuel lines (that remained under pressure), a 1 MV duct bank, a fiber optic conduits, and a traffic signal wire.